March 2021 saw completion of the redevelopment of 75,000 sq/ft of creative workspace at The Forge, Woking.
On this project Paul Earl Limited were contracted by Thirdway Contracts to carry out the full design and build Electrical Installation to Shell, Core & CAT A including Fire and Security Packages.
The project comprised the redevelopment of five floors of office space plus basement. Our works included new containment, distribution, power, lighting, fire and security throughout plus EV points to basement car park
Project Information
Client: Mayfair Capital
Development Manager: V7 Asset Management
Project Duration: 40 Weeks
Main Contractor: Thirdway Contracts
Paul Earl Team
Project Manager: Chris Foote
Site Manager: David Foote
Cost Manager: Lee Matthews
Key Suppliers
Fire and Security: Security Assured Ltd
Lighting: 299 Lighting
Lighting Controls: CP Electronics
Services Provided
Electrical Installation, Power Systems, Exposed and Concealed Containment, Suspended and Recessed LED Architectural Lighting Systems, Emergency Lighting, Fire and Security, EV Charging Points, Distribution Systems and Panels.